Parcel Orders over $300 Ship Free.
Steel-It-Epoxy-Finish-2-Quart-Kit-4907Q

Steel-It Epoxy Finish 2 Quart Kit 4907Q

Perma-Patch-Asphalt-Patch-60lb-Bag

Perma-Patch Asphalt Patch 60lb

Steel-It Epoxy Primer 2 Quart Kit 4210Q

STEEL-IT 4210Q 2-component epoxy precoat with 316L stainless flake. 2 quart kit, Parts A and B. Goes under 4907 topcoat.

  • 2 quart kit, model 4210Q
  • Mix 1 to 1; 45 minute induction; 6-8 hour pot life
  • 2 gallon kit listed separately; 4907 topcoat is a different product
$201.96
Availability: Out of stock

STEEL-IT 4210Q Epoxy Precoat 2 Quart Kit

STEEL-IT 4210 is the 2-component epoxy precoat with 316L stainless leafing pigment. This 2 quart kit is Parts A and B under 4907 topcoat on steel, aluminum, and plant equipment. Recoat sits in a 12-24 hour window. Pot life after mix is 6-8 hours. Apply at 50-100 F. The same precoat is also the 2 gallon kit. 4907 topcoat is listed separately. Follow the current STEEL-IT data on the job.

Looking for another size?

Looking for the epoxy topcoat?

Key Features

  • 2-component epoxy precoat with 316L stainless leafing pigment
  • 2 quart kit, model 4210Q, Parts A and B
  • Mix 1 to 1; wait 45 minutes; 6-8 hour pot life
  • Recoat 12-24 hours onto 4907 topcoat
  • Typical one coat at 3 mils dry under the topcoat
  • 2 gallon kit listed as the other pack

Applications

  • Smaller first-coat jobs before 4907
  • Plant equipment and washdown rooms
  • Chemical and marine work that needs the epoxy system

Technical Specifications

Property Value
Manufacturer STEEL-IT
Product 4210 Epoxy Precoat
Model 4210Q
Pack 2 quart kit, A+B
Mix 1:1 by volume
Induction 45 minutes
Pot life 6-8 hours
Apply 50-100 F, RH under 85%
Dry to touch 2 hours
Recoat 12-24 hours
Coverage about 215 sq ft/gal at 3 mils
Topcoat 4907, listed separately

Product documents: STEEL-IT 4210 / 4907 Epoxy System

Frequently Asked Questions

What is this?
STEEL-IT 4210Q, a 2 quart kit of 2-component epoxy precoat with 316L stainless flake.

How do I mix it?
Agitate A and B, mix 1 to 1, wait 45 minutes, then spray. Pot life is 6-8 hours.

Recoat window?
12-24 hours onto 4907. If you miss 24 hours, scuff with 200 grit.

Other pack?
The 2 gallon kit. 4907 topcoat is listed separately. This is not the polyurethane.

Who makes it?
STEEL-IT (Stainless Steel Coatings, Inc.).